πCertification of Inspection certificate:
π·An inspection certificate cannot be certified before the work starts.
πWhy?
β
1. Inspection certificates confirm completed or inspected work
π§An inspection certificate is issued after the inspector verifies that:
*Materials are correct
*Work is completed according to the drawing/spec
*Quality meets standards
*Safety and workmanship are acceptable
π§If the work has not started, there is nothing to inspect.
β 2. Issuing before work begins is considered invalid
Certifying before work is done can:
*Create legal and contractual problems
*Hide quality issues
*Cause rejection by consultants/clients
*Be treated as falsification
β
3. What can be issued before work starts?
π§Before work begins, only these can be issued:
*Inspection Request (IR) β mentioning βwork ready to startβ
*Method Statement
*Material Approval (MAR/MIR)
*Work Permit / Permit to Start Work
β Recommendation
βΊIf your team or contractor is asking for inspection certificate early, tell them:
π«Inspection certificate can only be signed after actual inspection.
β‘οΈPlease complete the work or prepare the section for inspection first.β