A vendor informs you that a critical material shipment will be delayed by three weeks, potentially impacting the project completion date. What should the project manager do FIRST?
Anonymous Quiz
A. Escalate the issue to the sponsor for immediate resolution
B. Implement fast-tracking on other activities to recover time
C. Perform an impact analysis on the schedule and cost
D. Replace the vendor immediately to avoid further delays