A project has a negative Schedule Performance Index (SPI < 1) and a negative Cost Performance Index (CPI < 1). This indicates:
Anonymous Quiz
A. Project is ahead of schedule and under budget
B. Project is behind schedule and over budget
C. Project is ahead of schedule but over budget
D. Project is behind schedule but under budget
1 comment
G G3️
Oct 19, 2025
B