π Why do projects exceed budget?
π·Letβs break it down with a real case!
π πΈCase Study: if let see just an example
πβΊA 4 km urban road project was initially estimated to cost 25 million ETB. Midway through execution, the cost escalated to 34 million ETB a 36% budget overrun.
Why?
βIncomplete BOQ during planning
βInflation not accounted for
βScope changes not managed
βInefficient procurement and material waste
π Key Lessons:
1οΈβ£ Accurate Quantity Take-Offs (QTO):
β€ Use updated drawings and software like AutoCAD & Excel or CostX
β€ Cross-verify QTO with field data
2οΈβ£ Rate Analysis:
β€ Include materials, labor, equipment, and overhead
β€ Use local market rates (e.g., from recent supplier quotes)
3οΈβ£ Contingency Planning:
β€ Add 5β10% contingency for risks like price hikes, delays, etc.
β€ Recalculate budget if major scope changes occur
4οΈβ£ Budget Monitoring Tools:
β€ Implement Earned Value Management (EVM)
β€ Compare Planned Value (PV), Actual Cost (AC), and Earned Value (EV)
5οΈβ£ Regular Financial Reviews:
β€ Monthly cost reports and cash flow updates
β€ Involve client & accountant in major budget revisions
π Pro Tip:
βCost estimation is not just math itβs strategic foresight!β