The project is falling behind schedule, and the team lead reports that they do not have enough skilled resources to complete a key task on time. What should the project manager do FIRST?
Anonymous Quiz
A. Cut a non-essential feature from the project scope.
B. Ask the team to work overtime to meet the deadline.
C. Meet with the team lead to assess the resource needs and current workload.
D. Immediately request more resources from the project sponsor.