A supplier delivers substandard sand. Your site team wants to use it to maintain schedule, arguing the defect is minor. The schedule is already delayed by 3 weeks, and replacing the supplier may cause further delays. What You should do?
Anonymous Quiz
A. Accept the material to avoid additional delay
B. Conduct a technical impact assessment on structural quality
C. Escalate to sponsor for decision
D. Reject material and order from a new supplier