👉FULL STEPS: CONCRETE CUBE TEST (From Beginning up to Testing)🚧1. Materials & Tools Required⏺Cement, sand, aggregate, water
⏺Cube moulds (150 mm × 150 mm × 150 mm usually)
⏺Trowel, vibrator or tamping rod
⏺Weighing machine
⏺Curing tank or water container
⏺Compression testing machine (CTM)
🚧2. Preparation of Cube Moulds⏺Clean the moulds.
⏺Apply
oil on all inside surfaces to avoid sticking.
⏺Assemble moulds tightly with bolts.
⏺Place moulds on a flat, rigid surface.
🚧3. Concrete Mixing🏷A. Measure materials⏺Cement, sand, aggregate based on mix ratio (e.g., 1:2:4, or M20, M25 etc.).
⏺Measure water using correct
water–cement ratio.
🏷B. Mix⏺Mix thoroughly until uniform (by hand or mixer).
🚧4. Filling the Cube Moulds⏺Fill the mould in
three layers.
⏺Tamp
25 times using tamping rod OR Vibrate for 5–10 seconds Each layer.
⏺Make sure no air voids are left.
⏺Top surface must be
leveled with a trowel.
🚧5. Initial Setting / Demoulding⏺Keep the filled moulds
undisturbed for 24 hours in a shaded place.
⏺After 24 hours, remove (demould) the cubes carefully.
🚧6. Curing⏺Place cubes in a
curing tank full of clean water.
⏺Temperature should be
20–27°C.
⚡️Cure for:
7 days test,
14 days test (optional),
28 days test (standard strength)🚧7. Testing on Compression Machine📍A. Preparation⏺Remove cube from water at least
1 hour before testing.
⏺Clean surface and measure dimensions using a vernier caliper (to find exact area).
📍B. Placement in Machine⏺Place cube on CTM between plates.
⏺Ensure
cast/leveled face is on top (smooth face facing upwards).
⏺Center the cube properly.
📍C. Load Application⏺Start the machine.
Apply load
gradually at a rate of:
140 kg/cm² per minute (or ~2.9 kN/s).
⏺Continue until cube
fails/cracks.
🏷8. Calculations❇️For a 150 mm cube:
Area = 150 × 150 =
22500 mm²⭐️Example:
Load at failure = 450 kN
Strength = 450,000 N / 22,500 mm² =
20 MPa📜9. ReportingInclude:
⏺Mix ratio / grade
⏺Cube ID number
⏺Age (7 or 28 days)
⏺Load at failure
⏺Compressive strength
Average of 3 cubes
Any visual observations of cracks