๐Program Evaluation and Review Technique (PERT)
๐ What is PERT?
โบThe Program Evaluation and Review Technique (PERT) is a project scheduling method that helps managers handle uncertainty in estimating task durations.
โบIt was developed by the U.S. Navy in the 1950s for the Polaris submarine project and has since been widely adopted in construction and engineering.
โถ๏ธUnlike the Critical Path Method (CPM), which assumes known activity durations, PERT is probabilistic,meaning it deals with variability in how long tasks may take.
๐ง How It Works
โบPERT uses three time estimates for each activity:
๐ข๐ฝ๐๐ถ๐บ๐ถ๐๐๐ถ๐ฐ(๐ข)-The minimum possible time to complete a task (if everything goes perfectly),Best-case scenario.
๐ ๐ผ๐๐ ๐น๐ถ๐ธ๐ฒ๐น๐(๐ )-The normal time you expect the task to take,Based on experience.
๐ฃ๐ฒ๐๐๐ถ๐บ๐ถ๐๐๐ถ๐ฐ (๐ฃ)-The maximum time the task might take (if things go wrong),Worst-case scenario.
๐ Why Use PERT in Construction?
โบConstruction projects often face uncertaintiesโweather, material delays, labor shortages, etc.
โบPERT helps: Account for risks in time estimation Provide more accurate schedules Improve planning and decision-making
๐Network Diagramming in Construction Projects
โบA Network Diagram is a graphical representation of a projectโs activities and their logical relationships. It shows what comes first, what follows, and what tasks depend on others.
๐ทThere are two main types of network diagrams:
๐งฉ A. Activity-on-Arrow (AoA)
Also called the Arrow Diagramming Method (ADM).
โ
Features:
โบArrows represent activities Nodes (circles or events) represent milestones or the start/end of activities.
โบActivities are defined by start and end points Often uses dummy activities (dashed arrows with zero duration) to show dependencies that cannot be represented otherwise.
๐ฐDummy Activity:
โบA placeholder arrow used for logic, not actual work. It helps maintain proper task relationships when two activities depend on a common predecessor.
๐ Limitations:
โบCannot easily represent lead and lag times
Less flexible than AoN for modern scheduling tools.
๐งฉ B. Activity-on-Node (AoN)
Also called the Precedence Diagramming Method (PDM),the most widely used in modern software like Primavera P6 and Microsoft Project.
โ
Features:
โบNodes (boxes) represent activities Arrows show dependencies or logic between them Allows for various dependency types:
Finish-to-Start (FS): Task B starts after Task A finishes
Start-to-Start (SS): Task B starts when Task A starts
Finish-to-Finish (FF): Task B finishes when Task A finishes
Start-to-Finish (SF): RareโTask B must start before Task A finishes.
๐งฉ C. Precedence Diagram
โบThis is simply the visual representation of an Activity-on-Node (AoN) method. It maps out:
โบAll project activities
Their logical sequences
Critical paths and floats/slacks
๐Each box (node) contains:Activity name,Duration,Early/latest start and finish dates &Total float
@etconp