🏗️ LABOUR PRODUCTIVITY IN CONSTRUCTION
Labour productivity is the amount of construction work completed by a worker or team per day.
1. Daily Work Output
1. Brickwork – 1 mason: 1.25 m³/day.
2. Plastering – 1 mason: 10 m²/day.
3. Tile Work – 1 mason + 1 helper: 8–10 m²/day.
4. Blockwork – 1 mason: 8 m²/day.
5. Formwork – 1 carpenter + 1 helper: 8–12 m²/day.
6. Reinforcement – 1 skilled worker + 1 helper: 1–1.5 tonnes/day.
2. Importance of Labour Productivity
- Labour cost estimation.
- Project scheduling.
- Manpower planning.
- Site performance monitoring.
- Improving construction efficiency.