🏗️ LABOUR PRODUCTIVITY IN CONSTRUCTION

Labour productivity is the amount of construction work completed by a worker or team per day.

1. Daily Work Output

1. Brickwork – 1 mason: 1.25 m³/day.
2. Plastering – 1 mason: 10 m²/day.
3. Tile Work – 1 mason + 1 helper: 8–10 m²/day.
4. Blockwork – 1 mason: 8 m²/day.
5. Formwork – 1 carpenter + 1 helper: 8–12 m²/day.
6. Reinforcement – 1 skilled worker + 1 helper: 1–1.5 tonnes/day.

2. Importance of Labour Productivity

- Labour cost estimation.
- Project scheduling.
- Manpower planning.
- Site performance monitoring.
- Improving construction efficiency.

👉ለ ኳንቲቲ ሰርቨይንግ እጅግ ጠቃሚ በተለይ Rate Analysis ስትሰሩ የሚያግዛቹ ስታንዳርዶች የያዘ መፅሃፍ ይፈልጋሉ?

🔆ስለ labour እና equipment UF(Utilization Factor) ከዚህ በተጨማሪ የ labour,Equipment እና machinery composition standard ወይ norms ጨምሮ Material consumption rate standard ያካተተ መፅሀፍ ከፈለጉ ከታች ባለው ሊንክ ያውርዱ👇

https://ye-buna.com/etconp?ref=product_detail&product=6a7ab12995479_etconp

Comments

Be the first to add a comment