You discover that a critical material was delivered late because the procurement team miscommunicated the required delivery date to the supplier. What should the project manager do FIRST?
Anonymous Quiz
A. Escalate the issue to senior management
B. Update the lessons learned register and risk register
C. Analyze how the delay impacts the project’s critical path
D. Replace the supplier for better performance