109.Consider activity-A, if everything goes extremely well, it can be completed in 6days but if everything occurs at its worst, it can be completed in 10days. Its most likely Completion time is assumed to be 8. What is the expected duration of activity A?
Anonymous Quiz
A. 12 days
B. 7 days
C. 9 days
D. 8 days