👉Site Engineer Quick Calculation Guide you uploaded, with details for each formula:
📐 Concrete Quantity
- Formula: 0.036 × Built-up Area (m²)
- Purpose: Quick estimation of concrete required based on total built-up area. Useful for preliminary planning.
🪚 Shuttering Quantity
- Formula 1: Concrete Quantity × 6
- Formula 2: 2.4 to 2.5 × Slab Area (m²) (includes column, beam & slab sides)
- Purpose: Helps calculate shuttering material needed for formwork.
🪵 Number of Plywood Sheets
- Formula: Shuttering Quantity × 0.22
- Purpose: Approximate count of plywood sheets required for shuttering.
🪵 Number of Battens
- Formula: Number of Plywood Sheets × 19.62
- Purpose: Estimate of battens needed to support plywood sheets.
🔩 Nails
- Formula: 0.075 × Shuttering Quantity (m²)
- Purpose: Quick calculation of nails required for fixing shuttering.
🧵 Binding Wire
- Formula: 0.075 × Shuttering Quantity (m²)
- Purpose: Used for tying reinforcement bars during concreting.
🛢️ Formwork Oil
- Formula 1: 0.065 × Shuttering Quantity (m²)
- Formula 2: 1 Litre for 15 m² (application rate)
- Purpose: Prevents concrete from sticking to shuttering, ensuring smooth removal.
🔗 Steel (Bars)
- First & Third Floor Slab: 4.425 Kg / Sq.ft
- Above Third Floor Slab: 6.625 Kg / Sq.ft
- Purpose: Quick thumb rule for reinforcement steel consumption depending on floor level.
✅ This guide is designed for site engineers to make fast, practical estimates without lengthy calculations. It’s best used for preliminary planning and quick checks before detailed BOQ preparation.