A motor grader has the following performance for one week: Total available hours: 50 Breakdown hours: 5 Operating hours: 40 Standard production rate: 100 m³/hr Actual production rate: 90 m³/hr Calculate OEE (%):
Anonymous Quiz
A) 72%
B) 68%
C) 65%
D) 70%
2 comments
Dawit Tsegaye
💎
Aug 31, 2025
0.81% is the answer
Ezana Biyazn
Sep 2, 2025
Available =40/50=0.8
performance=90/100=0.9
OEE=0.8*0.9=0.72=72%
performance=90/100=0.9
OEE=0.8*0.9=0.72=72%